CLL were engaged for emergency works when the residential properties waterline burst causing the residents bank to slip away. CLL completed the emergency slip stabilisation works by pinning down geotextile matting over slip scarf, installing the silt fence at the base of the property and then grass seed and mulch were used over the uncovered topsoil.
This work was done to prevent from further damage to the site while consenting and planning were underway.
Once all consents were received CLL completed the final works for the property, including retaining and slip stabilisation to ensure the residents could have the use of their land back.
CLL completed this job right from the emergency works through design and build, consenting process and the final works. Great work from all parties involved