CLL completed piling works for the new buffer piles at the entrance to the dry dock on behalf of Total Marine at the Lyttelton Port.
Wor … Click to read more
Catalina Bay Crib Wall Remediation
Hobsonville
CLL were engaged by LT McGuiness to Install over 200No, 9m Long Soil Nails. The initial methodology was to construct these nails using a rope acces … Click to read more
Akarana Yacht Club
Auckland
This job required the use of specialised Continuous Flight Auger (CFA) piling used in soft ground without the need to install casing. A 25 tonne Le … Click to read more
94-96 Queen St
Auckland CBD
CLL’s challenge was to lay the foundations in a low headroom confined space underneath an historical building requiring a seismic upgrade.
< … Click to read moreRymans Verrans Corner
North Shore, Auckland
CLL is carrying out the piling for this large retirement village complex. The piling involves about 6km of 600mm diameter piles under all structure … Click to read more
Sentinel Road
Herne Bay, Auckland
The owner of this multi-million dollar property chose to repair this slip on to the beach as it came within the property line. Access to and from t … Click to read more
Lake Pupuke
Takapuna, Auckland
CLL used its air operated downhole hammer for the 800mm diameter piles to retain the basement excavation of a building. A downhole hammer was requi … Click to read more
Main Rd
Kumeu
The culvert is about 120m long and about 10m wide and consists of reinforced concrete piles and a precast concrete deck system with a concrete top. … Click to read more
Wyuna Bay
Coromandel
This job was piling for a residence at remote Wyuna Bay north of Coromandel township, which had difficult access and a limited building platform. T … Click to read more
Hobsonville Rd
Hobsonville
This was an area of unuseable land which required improvement to build a structure on it. CLL provided CFA piling up to 25m which is rare for this … Click to read more
Tauranga Crossing
Tauranga
Tauranga Crossing is a shopping mall undergoing extensions to more than double it in size with a cinema to be incorporated and a number of large re … Click to read more
Union & Co Apartments
Auckland CBD
The challenges involved in this job included working on a site which traversed many levels. A level piling platform was not possible so works were … Click to read more
Wadestown
Wadestown
A major earthquake left all the retaining wall posts hanging in mid-air off a cliff. CLL removed concrete from the posts to take some load off, mad … Click to read more
Union Green Apartments
Auckland CBD
CLL built a concrete palisade wall to a basement, retaining 8.5m. Building piles from 600mm up to 1350mm diameter were drilled up to a maximum of 2 … Click to read more
Don Buck Rd
Massey, Auckland
CLL constructed an anchored reinforced concrete palisade retaining wall. The ground was very wet and almost collapsing. To remedy CLL needed to use … Click to read more
Alma St
Newmarket
A perimeter retaining wall of the full building site was required to allow excavation for the basement. Secant piling was carried out at the site w … Click to read more
City Rail Link
Downtown Auckland
CLL provided crane hire, concrete pump hire, supervision for CFA piling, health and safety for the CFA piling and carried out small lump-sum portio … Click to read more
Summerset Retirement Village
Mt Wellington
CLL was commissioned for core-barrelling into basalt to create about 140 five-metre building piles, ranging from 750mm, 900mm to a metre at the Har … Click to read more
Hayward Substation
Upper Hutt
Contract Environmental (visit www.cenv.co.nz ) a subsidiary of CLL Service and Solutions, were contracted to … Click to read more
Huntly Bypass
Huntly
CLL was engaged by Fulton Hogan to build debris protection racks for the culverts in the Huntly section of the Waikato Expressway.
CLL was … Click to read more
Kingsland Rail Underpass
Kingsland
Kingsland Rail Underpass CLL contracted to Hawkins Infrastructure to carry out the installation of a new underpass to the Kingsland Railway Station … Click to read more
Ryman Healthcare Petone
Petone
CLL completed Stone Columns for Ryman Healthcare, Petone, Wellington . CLL completed a total of 12,625 stone columns for buildings 01 and 02 in thi … Click to read more
Wellesley St Cycleway and Underpass
Auckland City
On behalf of Hawkins Infrastructure CLL completed works for the Wellesley Street Bridge cycleway and underpass.
The works invol … Click to read more
Canada Cycle Street
Auckland CBD
On behalf of Hawkins Infrastructure, CLL were proud to be apart of Auckland’s iconic Canada Street Bridge, the Light Path cycle way. CLL’s wor … Click to read more
Wynyard Quarter
Wynyard Quarter
On behalf of Fletchers, CLL completed the foundation works for a 16,735 square metre building which, will have a level of retail space and six lev … Click to read more
Auckland Rail Electrification
Auckland
CLL was engaged to install foundations for masts for the electrification of the Auckland Railway. Work involved installation of approximately 2600 … Click to read more
Kaimai Tunnel
Kaimai
CLL have completed a diverse scope of works over the last three years on behalf of Kiwirail for the Kaimai tunnel, this being:
- Bulk cl … Click to read more
Khyber Pass
Newmarket, Auckland
CLL was contracted to complete all foundation works for a six level apartment block, compromising of 59 apartments with two levels of basement car … Click to read more
Warkworth Town Hall
Warkworth
CLL was approached by CANAM construction to complete remedial foundation works for Warkworth’s historic town hall. The scope of works meant that … Click to read more
Waikato Hospital
Hamilton
On behalf of Hawkins, CLL completed the piling works for Waikato hospital.
The works included driving 300UC beams up to 30m de … Click to read more
Fred Thomas Drive
Takapuna
CLL were engaged by Kalmar to drive and install 64no 36m UC beams into ground for the construction of a four level multi-story car park with retail … Click to read more
Attwood Emergency Works
North Shore
CLL were engaged for emergency works when the residential properties waterline burst causing the residents bank to slip away. CLL completed the eme … Click to read more
Wineworks
Onehunga
Wineworks is the largest Wine bottling facility in Australasia, the building is a 16,000m2 warehouse in Onehunga, Auckland. WineWorks offers wine b … Click to read more
St Judes Drainage
Avondale, Auckland
CLL were engaged by HILOR, as experts in working in and around the rail corridor, to complete a storm water realignment around the position of a pi … Click to read more
Chonny Crescent
Manurewa, Auckland
CLL was engaged by Kidd Contracting to complete the retaining walls for a new commercial build in Industrial South Auckland. The retaining works in … Click to read more
Herne Bay Marine Piling
Herne Bay
Marine piling completed by CLL. CLL, on behalf of Boyd Cox Construction Ltd constructed foundations for a boat shed beneath a clifftop property in … Click to read more
Flaxdale Rd Bridge
Birkdale
CLL were engaged to complete the works for a residential bridge, which was access to five residential properties. The existing bridge was failing a … Click to read more
Rymans Birkenhead Curve Wall
Birkenhead
CLL completed a soil nail stabilised excavation connecting a precast concrete wall. This involved excavating down in four stages and installing 8m … Click to read more
CFA Installed Multipoles
Countdown Mangere
The Advantages
High load bearing capacity suitable for commercial projects – up to 2,000kN (ULS).
The process is … Click to read more
Bute Rd Apartments
Browns Bay
CLL completed the ground works at Browns Bays new apartment complex. These works included three different types of piling. Driven steel piles reinf … Click to read more
Bunnings Grey Lynn
Grey Lynn
CLL completed all foundation and retaining pile work for Bunnings new store in Grey Lynn, Auckland.
The foundation work consist … Click to read more
Te Atatu Interchange Noise Walls
Te Atatu
On behalf of Fulton Hogan, CLL completed the noise walls at the Te Atatu Interchange for the North Western Motorway upgrade.
CLL completed … Click to read more
2 DEGREES CELL TOWER INSTALLATION
Upper North Island
On behalf of Infratel Networks Limited, CLL constructed 35 pile foundations as part of the 2degrees cell phone tower upgrade. These works were comp … Click to read more
Te Puru Pump Station
Te Puru, Whitford
On behalf of Hawkins, CLL constructed a poured insitu waste water holding tank.
The project called for installation of temporar … Click to read more
Clifton Rd
North Shore
On behalf of Clifftop Services Limited CLL designed an in ground wall and soil nailed slope system to create a stable building platform for 1 Clift … Click to read more
RANGARIRI SH-1 PYLON RELOCATION
SH1 Rangariri
On behalf of Electrix Limited, CLL constructed three pile foundations and refurbished an existing pylon foundation. These works were completed as p … Click to read more
Brigham Wharf
The Brigham Street Bridge forms part of the Wyndham quarter wharf, the bridge is contained within the Auckland City Councils Roading network and is … Click to read more