CLL were engaged to complete piling works, capping beam, grouted stand anchors as well as reinstatement of concrete path and decking. CLL completed:
• 17no Reinforced concrete piles. These piles were 600 diameter and 16 meter deep.
The Grouted Strand Anchors
• 8no Grouted Strand Anchors which were 25 meters lo
Reinstatement
• concrete path and reinstate 120m2 of decking