CLL completed piling works for the new buffer piles at the entrance to the dry dock on behalf of Total Marine at the Lyttelton Port.
Works involved completing 4no 800dia piles through water upto 7m deep, silt upto 5m deep and 5m into bedrock. All works were completed off a barge using CLL’s Bulroc 800dia Down the hole hammer on our Soilmec SR-45 drill rig.