On behalf of Hawkins, CLL completed the piling works for Waikato hospital.
The works included driving 300UC beams up to 30m deep in 12m lengths. Each length welded and the piles extended with certified welds as required to achieve specification required.
All piling completed with a 60T crane with a 8T drop hammer and with excavator mounted vibe.