On Behalf of ASPEC Construction, CLL were required to complete 606 Piles in total. Depths ranging from 2m to 7m. Displacement rigid inclusion piles. (DRI Piles)
Equipment used:
- ABI 14/18
- SKP 80 Concrete pump
- 14T excavator (Support Machine for spoil, concrete plunger, and tremie hopper to bell the top of piles)
- 3T Excavator (to excavate to cut-off level before belling)
- Dumper (moving spoil from pile locations to stockpile area)
- EWP/Cherry Picker (support for ABI daily maintenance; Greasing, cleaning the goose neck in case of concrete blockages)